Environmental programme

Altai-Koks started implementation of NLMK Group’s environmental programme to be completed before 2020.

The programme is part of the Group’s Development Strategy and is aimed to further minimize the environmental impact and to achieve the best environmental performance standards in the global steel industry.

200 m RUR

total investments in environmental projects

Key environmental projects

2016

Revamping of dedusting systems for car dampers at coal preparation section 1. The increase in dedusting efficiency will reduce dust emissions by 20 tonnes per year.

2017

  • Construction of a neutralizing station for excess circulation gases from CDQ facilities of Coke Section No. 2 This will reduce carbon oxide emissions by two times.
  • Revamping of dedusting systems at coke-screening plant No. 2. Completion of this project will help to reduce coke dust concentration in the air of working area and dust generation at dust screening plants by almost 50%.